A timely warning regarding liquidated damages

I thought it might be timely to remind everyone to take care when filing out and completing construction contracts and repeat the cautionary tale of Temloc v Errill Properties [1987] 39 B.L.R 30, CA. 

In this case "£Nil" was inserted in the liquidated damages clause.  The employer claimed that it was entitled to claim general unliquidated damages as there was no liquidated damages clause in the contract.  The Court of Appeal disagreed and held that by inserting "£Nil" in the contract, liquidated damages were deemed to apply and as such were the employer's exhaustive remedy in relation to delayed completion.  The result was that the employer could not claim any damages for the delayed completion of the works. 

Our content explained

Every piece of content we create is correct on the date it’s published but please don’t rely on it as legal advice. If you’d like to speak to us about your own legal requirements, please contact one of our expert lawyers.

Tags

Mills & Reeve Sites navigation
A tabbed collection of Mills & Reeve sites.
Sites
My Mills & Reeve navigation
Subscribe to, or manage your My Mills & Reeve account.
My M&R

Visitors

Register for My M&R to stay up-to-date with legal news and events, create brochures and bookmark pages.

Existing clients

Log in to your client extranet for free matter information, know-how and documents.

Staff

Mills & Reeve system for employees.