Another warning on Final Certificates under JCT Contracts

JCT 2011 unamended contracts contain a provision that the Final Certificate is conclusive on a number of issues.

There is one proviso to this and the matters in any adjudication, arbitration or other (which would include court) proceedings commenced within 28 days after the Final Certificate has been issued.

What happens though if say court proceedings are issued within 28 days and later on one of the parties wants to issue arbitration proceedings in relation to matters not addressed in  the court proceedings?  After all, the Construction Act says that adjudication proceedings can be commenced at any time.

In the recent case of the Trustees of the Marc Gilbard 2009 Settlement Trust, the court made it clear it would not allow this to happen. It said:

  • A party who commences adjudication proceedings within 28 days of the issue of the Final      Certificate will be able to, either at the same time (by way of protective proceedings) or subsequently, issue court or arbitration proceedings, but only on the matters addressed in the adjudication and only within 28 days of the adjudicator’s decision.
  • Otherwise only one set of court or arbitration proceedings can be commenced within the 28 days of the Final Certificate. No further proceedings (be they adjudication or otherwise) can be commenced after the 28 days has passed. 

Our content explained

Every piece of content we create is correct on the date it’s published but please don’t rely on it as legal advice. If you’d like to speak to us about your own legal requirements, please contact one of our expert lawyers.

Posted by

Tags

Mills & Reeve Sites navigation
A tabbed collection of Mills & Reeve sites.
Sites
My Mills & Reeve navigation
Subscribe to, or manage your My Mills & Reeve account.
My M&R

Visitors

Register for My M&R to stay up-to-date with legal news and events, create brochures and bookmark pages.

Existing clients

Log in to your client extranet for free matter information, know-how and documents.

Staff

Mills & Reeve system for employees.